The Grenfell Tower Inquiry Podcast - 131 The Tenant Management Organisation: Week 2

131 The Tenant Management Organisation: Week 2

Download 131 The Tenant Management Organisation: Week 2

There was a surprising start to the week when it was revealed the TMO's Director of Assets and Regeneration, Peter Maddison, failed to submit evidence to the Inquiry until four days before he was due to be questioned.  It also emerged that Claire Williams from the TMO had ‘binned’ notebooks from her time working on the project.

Peter Maddison admitted talking to the main contractor Rydon about saving £800,000 from the project costs, before the formal results of the tender process were announced.

The inquiry heard how Claire Williams asked the main contractor for details of the fire performance of the cladding system several times.

Presenter / Producer: Kate Lamble
Producer: Luke Radcliff
Researcher: May Cameron

Published on Friday, 23rd October 2020.